04/09/2026 · 7 min read

How long does a restaurant have to close for a ventilation installation

Usually one day, not a week. How we plan installation in a venue that's already running, what can be done alongside guests, and when closing really can't be avoided.

This is the question that decides things more often than price. The owner knows the ventilation needs sorting — steam hangs in the kitchen, the staff struggle, guests can smell it in the dining room. And still it gets put off for a second year. The reason is almost always the same: the picture of the venue closed for two weeks.

That picture is expensive. A restaurant with a kitchen that closes for two weeks loses thousands of euros in revenue — tens of thousands for a larger venue. Add what can't be put into numbers: guests who found somewhere else in the meantime, and staff who earn nothing for two weeks. So the decision gets postponed — and the problem doesn't get better in the meantime.

The answer is simpler than people expect. In most venues one day is enough.

How we plan it

The schedule is as much part of the solution as sizing the ducts. In a working venue it's even harder — which is exactly why we deal with it from the start, not when we're standing on site with our tools.

  • We come for a survey. Free and without obligation, anywhere in Slovakia.
  • We prepare a quote based on what we saw on site.
  • We do follow-up measurements when they're needed — not every time. A second visit before installation isn't the rule; an agreed plan is.
  • We align two calendars — your operating one and our installation one. Not the other way round.
  • We split the work into what can run alongside service and what can't.
  • The rest we schedule for the evening, the night, your day off or after closing.

We coordinate with your production cycle, not just your opening hours

Opening hours are only the top layer. A kitchen has its own schedule that can't be seen from outside: morning prep, the lunch rush, the afternoon lull, evening service, cleaning and sanitation, deliveries. An installation company that only knows the opening hours will inevitably collide with one of these.

So before installation we go through three things with you at once: the venue's opening times, the kitchen's production schedule and our work sequence. The plan comes out of that. Noisy and dusty work goes into quiet periods or outside service, work above the cooking zone into times when nobody is cooking, and material deliveries outside your goods-in times, so we don't block each other's entrance.

The goal is zero days closed. Where that's technically impossible, it's one day — the one you choose, usually your regular day off. The difference from an ordinary installation isn't speed, but that the work is planned around your venue, not the other way round.

What can be done while guests are in the dining room

Most of the installation happens where a guest never goes. Ducting in the attic, a unit on the roof, ducts and a fan on the façade, penetrations through the structure — all of this can be done during opening hours without guests noticing.

At the Village restaurant in Bátka we installed three supply systems totalling 6,000 m³/h and two extraction systems totalling 7,000 m³/h this way. Most of the work was done in the attic and on the roof, during normal service. The restaurant was closed for a single day.

When closing can't be avoided

We won't claim it can always be done without interruption — that would be a promise nobody can keep. Some work simply can't be done above a hot cooking line and among the cooks: connecting the hoods, work directly above the cooking zone, breaking through a penetration in the kitchen.

These things need an empty kitchen. The difference is that it's hours, not weeks — and they can be concentrated into one day that you choose. Most often it's your regular day off, so the venue doesn't even lose that.

Why we say it up front

Because a closure date is a real cost for the owner, who has the right to know it in advance, not find out on site. During the survey we tell you how many days it will take and which work needs an empty venue. If anything comes up during installation that changes the schedule, you hear about it immediately, not after the fact.

We see this as part of the agreement, not as an extra favour. Keeping the time we spend getting in your way to a minimum is our commitment.

The plan is a commitment, not an estimate

Before installation one document is produced: who does what and when. The sequence of work, the days and hours we're in the venue, what needs an empty kitchen and when you return to normal operation. You approve this plan, and we stick to it.

We require the same of the suppliers who join the job with us. A deadline that slips for one of them slips the whole chain — and your venue pays for it, not us. That's why keeping to the schedule is a condition of working with us, not a polite phrase in a quote.

If you think ventilation means weeks of dust, mess and a closed restaurant — you haven't worked with us yet.

When is the best time

The cheapest moment is while the space is being prepared, when the walls are bare and the ceilings open — then the venue doesn't stop at all, because it isn't running yet. The second good moment is when appliances are being replaced or the kitchen altered, when a shutdown is planned anyway. Then the ventilation can be sorted “while we're at it” and the day of closure isn't counted twice.